Projects
RUWAIS -DIYAB GAS DEVELOPMENT PROJECT
Client: AL MANSOORI Production Services/ADNOC
Location: RUWAIS
Year: Completed from 2024 to 2025 (10 months)
Scope:
Engineering, Procurement, and Construction:
Well site.
Gas production pipeline.
Pilot production facilities.
Natural gas export pipeline.
In instrumentation, control systems, and produced water treatment. Installation of necessary equipment such as separators, compressors, amine units, TEG units, fuel gas systems, and leak detection systems.
Unconventional Pilot Project – UC-02HUP-02 Early Production Facility
Client: ADNOC
Location: Huwaila
Year: 2025-2026 (19 months) DBOOM – Continued
Scope:
Pressure testing during construction includes investigation, NOC of pipeline routes, and site preparation.
Design, detailed engineering, procurement, supply, urgent delivery, logistics, and transportation of relevant oilfield pressure gauges.
Manufacturing, construction, installation, testing, and achieving mechanical completeness.
Pre debugging, debugging, startup, site performance testing, operation and maintenance.
Main high-pressure SEWA 30 inch natural gas pipeline diversion
Client: Sharjah Road and Transport Authority (SRTA)
Location: Sharjah UAE Road
Year: 2021-2022 (8 months) Completed
Scope:
Provide and construct instrumentation for a 30 inch CS natural gas pipeline section.
Hot tap is effective
Horizontal directional drilling (HDD)
Steel sheet pile and excavation
Joint civil engineering completed.
ADNOC-Recovering Habshan-III Hydrocarbon flare Gas
Client: PETROFAC/ADNOC
Location: Habshan
Year: 2022-2024 (completed)
Scope:
Procurement of air pressure for civil engineering and participation in technical construction.
Procurement, manufacturing, painting, and installation of steel structure engineering.
Manufacturing, welding, painting, installation, and testing of pipelines and short pipes.
Installation of pneumatic instruments and equipment. The provision of welding equipment..
64 “Torch Pipeline Shutdown Activity (Completed)